Capital Development Board met December 10

Webp meeting 07

Capital Development Board met Dec. 10.

Here is the minutes provided by the board:

The meeting of the Capital Development Board was held by video-conference at the James R. Thompson Center, 100 West Randolph Street, Suite 14-600, Chicago, Illinois, the Stratton Office Building, 401 South Spring Street, Third Floor, Springfield, Illinois and the Illinois Department of Transportation Office, 1102 East Port Plaza, Collinsville, Illinois.

Chicago

Eileen Rhodes, Chair

David Arenas

Pam McDonough

Martesha Brown

Springfield

Beverly Potts

Collinsville

Glyn Ramage

Others present:

Chicago

Jim Underwood, CDB

Amy Romano, CDB

Ron Wright, CDB

Brent Lance, CDB

Mike Wilson, CDB

Karla Springer, CDB

Jesse Martinez, CDB

Andres Padua, CDB

Sally Finney, CDB

Kathryn Martin, CDB

Mohammed Haq, CDB

Sean Reeder, UofI

Andrea Bauer, CDB

Camille Yu, Holabird & Root

Emily Zgonjanin, CDB

Keith Moore, CDB

Natasia McDade, CDB

Joey Moore, Carmona Strategic Solutions

Roberto Carmona, Carmona Strategic Solutions

Nicole Scott, CDB

Nia Jones, CDB

Peter Dombraugh, Knight Engineering Architects

Leonard McGee, CDB

Joe Saftig, IHC Construction

Springfield

Heather Bova, CDB

Marcy Joerger, CDB

Lisa Hennigh, CDB

Paul Kmett, CDB

Tim Patrick, CDB

James Cockrell, CDB

Jen Boen, CDB

Amber Dooley, CDB

Steve Law, Fuhrman Engineers

Dennis Hostetter, Fuhrmann Engineers

Gwen Diehl, IDVA

Art Moore, CPO

Jody Hunt, CDB

Erin Eoff, CDB

Ken Morris, CPO

Jake Teegarden, CDB

Heidi Hildebrand, CDB

Marcy Joerger, CDB

Crystal Kitchen, CDB

Josh Hansen, CDB

Lisa Hennigh, CDB

The meeting was called to order at 11:05a.m.

Heather Bova took roll call. For the record, Chair Eileen Rhodes and members David Arenas, Pam McDonough and Martesha Brown were present at the Chicago meeting site and Glyn Ramage was present at the Collinsville meeting site. Beverly Potts was present in Springfield.

Pam McDonough moved and David Arenas seconded a motion for the adoption of the agenda. Chair Rhodes called for a vote, and the motion was approved unanimously.

Pam McDonough moved and Glyn Ramage seconded a motion to approve the minutes of the November 13, 2019 meeting. Chair Rhodes called for a vote, and the motion was approved unanimously.

All attendees and guests in Chicago and Springfield introduced themselves to the Board. There were no guests in Collinsville.

Mr. Wright presented the following Proceed Order to the Board:

PROCEED ORDER – VETERANS’ HOME FACILITY CHICAGO

Illinois Department of Veterans’ Affairs Construct 200 Bed

Chicago, Cook County, Illinois

CDB Project No. 040-080-001

A/E: Harley Ellis Devereaux

Proceed Order for IHC Construction Co., LLC.$164,289.78

Martesha Brown moved and Pam McDonough seconded a motion to approve the Proceed Order. Chair Rhodes called for a vote, and the motion was approved unanimously.

Mr. Wright presented the following Proceed Order to the Board:

PROCEED ORDER – ILLINOIS VETERANS’ HOME CHICAGO

Illinois Department of Veterans’ Affairs Construct 200 Bed

Chicago, Cook County, IL

CDB Project 040-080-001

A/E: Harley Ellis Devereaux

Proceed Order for IHC Construction Co., LLC.$1,400,940.64

Pam McDonough moved and David Arenas seconded a motion to approve the Proceed Order. Chair Rhodes called for a vote, and the motion was approved unanimously.

Mr. Wright presented the following Modification to the Board:

Modification –Illinois Department of Human Services Shapiro Developmental Center

Upgrade Steam and Condensate Lines

Kankakee, Kankakee County, Illinois

CDB Project No. 321-100-126

A/E: Henneman Engineering Inc.

Modification for Henneman Engineering Inc.$276,272.00

Martesha Brown moved and Pam McDonough seconded a motion to approve the Modification. Chair Rhodes called for a vote, and the motion was approved unanimously

Mr. Wright presented the following change Order to the Board:

Change Order – Prairie State College Illinois Community College Board HVAC and BAS Renovation

Chicago, Cook County, Illinois

CDB Project No. 810-076-013 Ph3

A/E: Planera Architects Inc.

Change Order for Heating – Ideal Heating Company.$165,476.15

Martesha Brown moved and Pam McDonough seconded a motion to approve the Change Order. Chair Rhodes called for a vote, and the motion was approved unanimously.

Mr. Lance presented the following two A/E selection recommendations from PSB 256:

Pam McDonough moved and Glyn Ramage seconded a motion to approve the selection of architects/engineers. Chair Rhodes called for a vote, and the motion was approved unanimously.

Mr. Lance presented the following thirteen A/E selection recommendations from PSB 257:

1.

007-010-024

Illinois Courts

Repair Driveway and Parking Lot Supreme Court of Illinois – Sangamon Springfield, Sangamon County, Illinois

1. Dewberry Engineers Inc.

2. Fehr-Graham&AssociatesLLC

3. FuhrmannEngineering,Inc

Appropriation: $692,800.00 Project Cost: $692,800.00

2.

102-779-018

Department of Natural Resources Rehabilitate State Park Sewage Treatment Systems and Area

Eldon Hazlet State Park – Clinton County

1. Benton & Associates, Inc

2. Bacon Farmer Workman Engineering

3. Horner & Shifrin, Inc.

Appropriation: $1,712,900.00 Project Cost: $1,712,900.00

3.

810-004-009

Illinois Community College Board

Replace Roofing System – Building 3

Black Hawk Community C 13ollege – Moline

1. Demonica Kemper Architects, LLC

2. Kenyon & Associates Architects, Inc.

3. Cordogan, Clark & Associates

Appropriation: $1,085,280.00 Project Cost: $1,447,040.00

4.

810-014-004

Illinois Community College Board Restore Exterior

Harold Washington Community College, Chicago

1. GSG-ProbeConsulting,Inc

2. Globetrotters Engineering Corporation

3. Bauer Latoza Studio Ltd

Appropriation: $1,743,750.00 Project Cost: $2,325,000.00

5.

810-018-008

Illinois Community College Board

Upgrade Laboratories

Olive-Harvey Community College – Chicago

1. Holabird & Root, LLC

2. Doyle & Associates Architects & Interior Design

3. Cordogan, Clark & Assoc, Inc.

Appropriation: $375,000.00 Project Cost: $

500,000.00

6.

810-026-015

Illinois Community College Board Replace Roofing System

Richland Community College, Decatur

1. Steckel-Parker Architects, Inc.

2. Prather Tucker Asociates, Inc.

3. Reifsteck Reid & Company Architects

Appropriation: $644,740.00 Project Cost: $859,653.00

7.

810-036-023

Illinois Community College Board Repair Bridge

Illinois Central College – East Peoria

1. MidwestEngineeringAssociates,Inc

2. Farnsworth Group, Inc

3. Bacon Farmer Workman Engineering & Testing, Inc

Appropriation: $150,000.00 Project Cost: $

225,000.00

8.810-048-025

Illinois Community College Board Upgrade elevators

Joliet Junior College – Will County

1. Kluber, Inc, Batavia, Il

Appropriation: $450,000.00 Project Cost: $600,000.00

9.

810-052-018

Illinois Community College Board Replace Waterline

Kaskaskia Community College – Centralia

1. WRFEngineersLLC

2. Hurst-Rosche,Inc.,EastStLouis,IL

3. Bacon Farmer Workman Engineering & Testing, Inc., Marion, IL

Appropriation: $750,000.00 Project Cost: $1,000,000.00

10.810-056-028

Illinois Community College Board Replace Roofing System

College of Lake County – Grayslake

1. Doyle & Associates Architects and Interior Designers, Chicago

2. GSG-Probeconsulting, Inc., Chicago

3. Globetrotters Engineering Corporation, Chicago

Appropriation: $1,125,000.00 Project Cost: $1,500,000.00

11.810-070-018

Illinois Community College Board Renovate Building E

Morton Community College – Cook County

1. Demonica Kemper Architects, LLC, Chicago2. Mode Architects, P.C., Chicago

3. 3 Bauhs Dring Main Ltd.,Chicago

Appropriation: $751,000.00 Project Cost: $1,503,825.00

12.810-088-013

Illinois Community College Board

Replace Boilers, Pumps and Condensing Units Southeastern Illinois College, Harrisburg

1. Asaturian, Eaton and Associates

2. Marcum Engineering, LLC, Marion

3. Farnsworth Group, Inc., St.Louis

Appropriation: $703,350.00 Project Cost: $937,800.00

13.830-030-161

University of Illinois

Repair Exterior – Science and Engineering South Buildings

University of Illinois – Chicago

1. Bauer Latoza Studio Ltd., Chicago

2. GSG-ProbeConsulting,Inc.,Chicago 3. Globetrotters Engineering Corporation, Chicago

Appropriation: $2,750,000.00 Project Cost: $2,750,000.00

Martesha Brown moved and Glyn Ramage seconded a motion to approve the previous recommendations for the selection of architects/engineers. Chair Rhodes called for a vote, and the motion was approved unanimously.

Mr. Lance presented the following Higher Education recommendation for A/E selection:

1.

830-010-346

Board of Higher Education

Masonry Reconstruction

University of Illinois, Urbana-Champaign

1. Doyle & Associates Architects and Interior Designers, Chicago

2. Johnson Lasky Kindelin Architects, Inc.

3. White & Borgognoni Architects, P.C.

Project Cost: $2,950,000.00

Pam McDonough moved and Glyn Ramage seconded a motion to concur the previous recommendations for the selection of A/E. Chair Rhodes called for a vote, and the motion was approved unanimously.

Mr. Lance noted the following Small Contract Architect/Engineer selection as an informational item:

1.

630-332-004

Department of Transportation

Replace Roofing System

District 5, Clinton Maintenance Storage Facility, DeWitt County

Project Cost: $175,000

Pam McDonough moved and Martesha Brown a motion to approve the previous recommendation for the selection of an A/E. Chair Rhodes called for a vote, and the motion was approved unanimously.

Pam McDonough moved and David Arenas seconded a motion to adjourn. Chair Rhodes called for a vote, and the motion was approved unanimously. The meeting adjourned at 12:05 p.m.