Lane's committee spent the most on storage in the quarter, with all those payments ($2,552) going to Public Storage in Chicago. Table 1 below shows the distribution of how Lane's committee spent its money in the fourth quarter.
Table 1: Fourth-quarter spending by purpose
Purpose
Amount
Percent of total spending
Storage
$2,552
93.4%
Floral arrangement
$180
6.6%
Table 2 below shows the top 4 largest single expenditures during the quarter.
Table 2: Largest expenses of the fourth quarter
Recipient
Date
Amount
Purpose
Public Storage
2016-12-02
$2,552
Storage
R & D Rausch-Clifford Florist
2016-12-30
$60
Floral arrangement
R & D Rausch-Clifford Florist
2016-10-20
$60
Floral arrangement
R & D Rausch-Clifford Florist
2016-11-03
$60
Floral arrangement