1.0 CALL TO ORDER
2.0 ROLL CALL
3.0 PUBLIC COMMENT
4.0 CHAIR
1. Approval of the Minutes of the Engineering, Planning & Development Oversight Committee Meeting held May 16, 2024.
2. Additional Items
5.0 EXECUTIVE DIRECTOR
1. Presentation: I-490/I-390 Interchange
2. Additional Items
6.0 ITEMS FOR CONSIDERATION
6.1 ENGINEERING
1. Award of Contract I-16-4669 to F.H. Paschen, S.N. Nielsen & Associates, LLC for Roadway and Bridge Construction on the Elgin O’Hare Western Access IL Route 390 and I-490 Interchange in the amount of $184,253,944.05.
2. Extra Work Order on I-20-4727 to Lorig Construction Company for Roadway and Bridge Construction on the Elgin O’Hare Western Access (I-490) between Mile Post 0.6 (Franklin Avenue) and Mile Post 1.0 (Illinois Route 19 (Irving Park Road)) in the amount of $6,000,000.00, increasing the upper limit of compensation from $150,343,311.91 to $156,343,311.91.
3. Acceptance of Proposal from Strand Associates, Inc. on Contract I-24-4947 for Design Services for Bridge Reconstruction Systemwide in an amount not to exceed $4,636,459.78.
4. Acceptance of Proposal from EFK Moen, LLC on Contract I-24- 4948 for Design Services for Bridge Rehabilitation on the Ronald Reagan Memorial Tollway (I-88) between Mile Post 44.5 (Howland Creek) and Mile Post 55.0 (US 52) in an amount not to exceed $3,856,898.94.
5. Award of Contract 24-0107 to RoadSafe Traffic Systems, Inc. for the purchase of Emergency Maintenance of Traffic Systems in an amount not to exceed $613,500.00 (Tollway Emergency).
6.2 LEGAL
1. Approval of an Intergovernmental Agreement with the Illinois Department of Transportation for work associated with I-190 Ramp F. Estimated cost to the Tollway: $5,211,800.00 which will offset the balance IDOT owes the Tollway.
2. Approval of an Intergovernmental Agreement with the Illinois Department of Natural Resources (“IDNR”). Cost to the Tollway: IDNR will pay the Tollway $541,889.27.
3. Authorization to Enter into a Settlement Agreement with Property Owner – Milwel, Inc.; Tollway Parcel No. WA-3D-12-048. Cost to the Tollway: As discussed in Executive Session.
4. Authorization to Enter into a Settlement Agreement with Chastain & Associates LLC. Cost to the Tollway: As discussed in Executive Session.
7.0 UNFINISHED BUSINESS
8.0 NEW BUSINESS
9.0 ADJOURNMENT